Complex concrete structures are at the heart of TNE Civil’s capability. We deliver formwork, reinforcement and concrete placement packages for major infrastructure, water, mining and renewable energy projects.

Our teams combine practical construction experience with in-house engineering, planning, commercial and HSEQ support. This allows us to manage technically demanding structures, complex temporary works and high-volume concrete pours from tender through to handover.

WHAT WE DELIVER

Complete FRP packages for complex structures.

• Steel reinforcement fixing
• Specialised single-sided wall formwork
• Suspended slabs
• Jump forms, climbing forms and slip forms
• PERI, Acrow, Uni-span and Doka formwork systems
• Falsework design and erection
• Concrete placement and finishing
• High-volume and large-volume pours
• Dive structures and liner walls
• Capping beams and bridges
• Culverts, tanks and pits

Morley–Ellenbrook Line
Morley–Ellenbrook Line
Yanchep Rail Extension
Yanchep Rail Extension
Thornlie–Cockburn Link
Thornlie–Cockburn Link
Woodman Point WRRF
Woodman Point WRRF
Stephenson Avenue Extension
Stephenson Avenue Extension
Project Ceres — CCR Building
Project Ceres — CCR Building
PROJECT EXPERIENCE

Demonstrated across major infrastructure projects.

• More than 20,000 m³ of concrete placed across the Morley–Ellenbrook Line dive structures
• Single-sided liner wall pours exceeding seven metres using PERI formwork
• 3.5 km of capping beams and twelve bridges on the Yanchep Rail Extension
• Sixteen wastewater treatment structures at Woodman Point WRRF
• Bridge, underpass and retaining-wall structures on the Stephenson Avenue Extension
• Structural concrete for the Project Ceres Central Control Room building